How is goal progress calculated?

Goal progress is based on two values:

  • Expected Progress: The system automatically updates based on the goal's timeline.
    Formula: Expected Progress = (Days elapsed since start date / Total duration of the goal) X 100
  • Actual Progress: Employee manually update during check-ins.

Example of automated goal status update:
If a goal runs from April 1 to April 30, then on April 15, the expected progress is 50%.

Progress Type

Condition

Goal Status

Actual Progress

≥ 100%

Achieved

Expected/Actual

≤ 16.5%

On Track

Expected/Actual

> 16.5% and ≤ 33%

Behind

Expected/Actual

> 33% (but Actual < 100%)

At Risk